- >Subject matter of the dispute: Legal reforms affecting the renewable energy sector
- >Amount claimed: EUR 61.3 million
- >Amount awarded: EUR 53.3 million
- >Valuation method: income-based approach (discounted cash flow)
- >Interest rate: host State's sovereign bonds (10-year)
- >Costs of arbitration: EUR 562,920.96 + SEK 6,867
- >Award legal costs: Claimant was awarded EUR 2.6 million (including full costs of arbitration)
- >Award costs of arbitration: Costs follow the award
ARBITRAL DECISION
15 February 2018 |
|
RECTIFICATION PROCEEDING
9 April 2018 |
ANNULMENT PROCEEDINGS
16 May 2018 - Decision of the Svea Court of Appeal (Swedish) 25 April 2019 - Decision of the Svea Court of Appeal - Swedish | English (unofficial translation) 27 May 2020 - Decision of the Svea Court of Appeal (unofficial translation) |
ENFORCEMENT PROCEEDINGS (United States)