- >Subject matter of the dispute: Claims arising out of Mongolia’s cancellation of claimant's mining and exploration licenses for a uranium deposit
- >AInvoked instruments: ECT and Foreign Investment Law of Mongolia
- >Amount claimed: USD 326 million
- >Amount awarded: USD 80 million
- >Valuation method: market-based approach (arm's length offer)
- >Interest rate: LIBOR + 2%
- >Costs of arbitration: EUR 634,882.37
- >Award legal costs: Claimant was awarded USD 9,074,143.51
- >Award costs of arbitration: Costs follow the award