- >Subject matter of the dispute: Thirteenth Amendment of Atomic Energy Act regarding the phase-out of nuclear power plants in Germany by 2022
- >Amount claimed:EUR 4.3 billion
- >Amount awarded: ZERO
- >Costs of arbitration: N/A
- >Award legal costs: Each party bears its own legal costs
- >Award costs of arbitration: Parties share costs equally
ARBITRAL DECISIONS
31 August 2018 2 July 2013 - Decision pursuant to ICSID Arbitration Rule 41(5) 9 November 2021 - Order of the Tribunal taking Note of the Discontinuance of the Proceeding
|