- >Subject matter of the dispute: Alleged actions by regulatory authorities and government agencies in relation to the pricing of electricity and compensation for public obligations in respect to renewable energy
- >BIT invoked: Austria-North Macedonia BIT
- >Amount claimed: EUR 160 million (USD 229.1 million)
- >Amount awarded: N/A
- >Costs of arbitration: N/A
- >Award legal costs: Each party bears its own legal costs
- >Award costs of arbitration: Parties share costs equally
ARBITRAL DECISION
2 September 2011