- >Subject matter of the dispute: Legal reforms affecting the renewable energy sector
- >Amount claimed: EUR 196,717,000
- >Amount awarded: ZERO
- >Costs of arbitration: USD 765,634.54
- >Award legal costs: Each party bears its own legal costs
- >Award costs of arbitration: Parties share costs equally