- >Subject matter of the dispute: Claims arising out of the alleged termination by the Government of electricity concessions held by the claimant, as well as the seizure of the assets owned by claimant's electricity companies
- >Amount claimed: N/A
- >Amount awarded: ZERO
- >Costs of arbitration: EUR 590,740.3
- >Award legal costs: Each party bears its own costs
- >Award costs of arbitration: Parties share costs equally
ARBITRAL DECISIONS
20 April 2016 | 31 March 2016 |
ANNULMENT PROCEEDINGS
26 February 2018 Judgment of the Svea Court of Appeal - Swedish | English (unofficial translation) |